Question
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
Options
- ATo identify responses to risks documented in the business case
- BTo identify information about the project environment and objectives
- CTo identify the roles to be involved in risk management activities
- DTo identify uncertainties that may impact on the delivery of the project objectives