PRINCE2-FOUNDATION Question #979: Real Exam Question with Answer & Explanation

The correct answer is D. To identify uncertainties that may impact on the delivery of the project objectives. See the full explanation below for the reasoning.

Question

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

Options

  • ATo identify responses to risks documented in the business case
  • BTo identify information about the project environment and objectives
  • CTo identify the roles to be involved in risk management activities
  • DTo identify uncertainties that may impact on the delivery of the project objectives