Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

The correct answer is D. To identify uncertainties that may impact on the delivery of the project objectives. See the full explanation below for the reasoning.

Question

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

Options

  • ATo identify responses to risks documented in the business case
  • BTo identify information about the project environment and objectives
  • CTo identify the roles to be involved in risk management activities
  • DTo identify uncertainties that may impact on the delivery of the project objectives

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    15% (4)
  • C
    8% (2)
  • D
    73% (19)