Which is an objective of the 'directing a project' process?
The correct answer is B. To ensure corporate or programme management has an interface to the project. See the full explanation below for the reasoning.
Question
Which is an objective of the 'directing a project' process?
Options
- ATo review and approve a project mandate
- BTo ensure corporate or programme management has an interface to the project
- CTo define how risks, issues and changes will be managed
- DTo obtain approval for completed products
How the community answered
(20 responses)- A5% (1)
- B80% (16)
- C5% (1)
- D10% (2)