PRINCE2-FOUNDATION · Question #972
Who represents the three project interests on a project?
The correct answer is D. Project board. See the full explanation below for the reasoning.
Question
Who represents the three project interests on a project?
Options
- AProject manager
- BProject support
- CExternal project stakeholders
- DProject board
How the community answered
(58 responses)- A7% (4)
- B14% (8)
- C5% (3)
- D74% (43)