Which is a minimum requirement for applying the organization theme?
The correct answer is A. To document the project management team structure. See the full explanation below for the reasoning.
Question
Which is a minimum requirement for applying the organization theme?
Options
- ATo document the project management team structure
- BTo define the experience required for each project role
- CTo include external stakeholders on the project board
- DTo train project team members in the use of PRINCE2
How the community answered
(32 responses)- A72% (23)
- B16% (5)
- C9% (3)
- D3% (1)
Community Discussion