How does the project board use the 'manage by stages' principle to control the project?
The correct answer is B. By reviewing project viability at defined intervals. See the full explanation below for the reasoning.
Question
How does the project board use the 'manage by stages' principle to control the project?
Options
- ABy approving the project management team
- BBy reviewing project viability at defined intervals
- CBy ensuring that the benefits are managed and controlled
- DBy reviewing previous project closure documentation
How the community answered
(33 responses)- A6% (2)
- B82% (27)
- C9% (3)
- D3% (1)