PeopleCert
PRINCE2-FOUNDATION · Question #960
Which describes a project benefit?
The correct answer is D. A measurable improvement resulting from an outcome. See the full explanation below for the reasoning.
Question
Which describes a project benefit?
Options
- AA specialist product of the project
- BThe result of a change derived from using the project's products
- CAn uncertain result caused by project actions
- DA measurable improvement resulting from an outcome
How the community answered
(17 responses)- A18% (3)
- B6% (1)
- C6% (1)
- D71% (12)
Community Discussion
No community discussion yet for this question.