Which describes a project benefit?

The correct answer is D. A measurable improvement resulting from an outcome. See the full explanation below for the reasoning.

Question

Which describes a project benefit?

Options

  • AA specialist product of the project
  • BThe result of a change derived from using the project's products
  • CAn uncertain result caused by project actions
  • DA measurable improvement resulting from an outcome

How the community answered

(17 responses)
  • A
    18% (3)
  • B
    6% (1)
  • C
    6% (1)
  • D
    71% (12)