PRINCE2-FOUNDATION · Question #96

It me Project Board are too busy to authorize all change requests themsekes they can appoint....?

The correct answer is A. A Change Authorty. See the full explanation below for the reasoning.

Question

It me Project Board are too busy to authorize all change requests themsekes they can appoint....?

Options

  • AA Change Authorty
  • BA Change Board
  • CA Change Commtee
  • DA Change Budget

How the community answered

(60 responses)
  • A
    70% (42)
  • B
    8% (5)
  • C
    17% (10)
  • D
    5% (3)