In which strategy would the change control process be recorded?
The correct answer is B. Configuration Management Strategy. See the full explanation below for the reasoning.
Question
In which strategy would the change control process be recorded?
Options
- AQuay Management Strategy
- BConfiguration Management Strategy
- CRisk Management Strategy
- DCommunication Management Strategy
How the community answered
(50 responses)- A16% (8)
- B74% (37)
- C8% (4)
- D2% (1)