Which of the following is a stable element within the Project Initiation Document?

The correct answer is C. Project tolerance. See the full explanation below for the reasoning.

Question

Which of the following is a stable element within the Project Initiation Document?

Options

  • ABusiness Case
  • BProject Plan
  • CProject tolerance
  • DRisk Log

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    81% (25)
  • D
    10% (3)

Community Discussion