PRINCE2-FOUNDATION · Question #91
Which of the following is a stable element within the Project Initiation Document?
The correct answer is C. Project tolerance. See the full explanation below for the reasoning.
Question
Which of the following is a stable element within the Project Initiation Document?
Options
- ABusiness Case
- BProject Plan
- CProject tolerance
- DRisk Log
How the community answered
(31 responses)- A3% (1)
- B6% (2)
- C81% (25)
- D10% (3)