PRINCE2-FOUNDATION · Question #90

The Project Board keeps a control of the project through: 1 Highlight Reports 2 Checkpoint Reports 3 Exception assessment 4 Quality Log

The correct answer is C. land 3 only. See the full explanation below for the reasoning.

Question

The Project Board keeps a control of the project through:

1 Highlight Reports 2 Checkpoint Reports 3 Exception assessment 4 Quality Log

Options

  • A1 3 and 4 only
  • BAll of the above
  • Cland 3 only
  • D1 2 and 3 only

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    73% (19)
  • D
    15% (4)

Community Discussion

No community discussion yet for this question.