PRINCE2-FOUNDATION · Question #900

Which is a minimum requirement for applying the plans theme?

The correct answer is B. The team managers in the project must prepare team plans. See the full explanation below for the reasoning.

Question

Which is a minimum requirement for applying the plans theme?

Options

  • AThe project must have at least two management stages
  • BThe team managers in the project must prepare team plans
  • CScope tolerance must be prioritized using MoSCoW
  • DThe project plan must be presented as a Gantt chart

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    84% (37)
  • C
    5% (2)
  • D
    9% (4)