PeopleCert
PRINCE2-FOUNDATION · Question #899
Which describes a risk event?
The correct answer is A. The area of uncertainty in terms of the threat or opportunity. See the full explanation below for the reasoning.
Question
Which describes a risk event?
Options
- AThe area of uncertainty in terms of the threat or opportunity
- BThe derivation or sources of a potential risk to the project
- CThe achievement of a milestone on the project plan
- DThe sequence of events and actions that will be put in place if a risk occurs
How the community answered
(41 responses)- A80% (33)
- B10% (4)
- C2% (1)
- D7% (3)
Community Discussion
No community discussion yet for this question.