PRINCE2-FOUNDATION · Question #892

Which process is used to define how baselines will be established and controlled?

The correct answer is D. Starting up a project. See the full explanation below for the reasoning.

Question

Which process is used to define how baselines will be established and controlled?

Options

  • AControlling a stage
  • BDirecting a project
  • CInitiating a project
  • DStarting up a project

How the community answered

(53 responses)
  • A
    13% (7)
  • B
    6% (3)
  • C
    4% (2)
  • D
    77% (41)

Community Discussion

No community discussion yet for this question.