nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #891

Identify the missing words in the following sentence. The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

The correct answer is A. the 'starting up a project' process is completed. See the full explanation below for the reasoning.

Question

Identify the missing words in the following sentence. The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

Options

  • Athe 'starting up a project' process is completed
  • Bthe project mandate has been approved by the project board
  • Cthe project board has agreed the project strategies
  • Dcorporate, programme management or the customer have authorized a project

How the community answered

(34 responses)
  • A
    82% (28)
  • B
    6% (2)
  • C
    9% (3)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice