Identify the missing words in the following sentence. The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.
The correct answer is A. the 'starting up a project' process is completed. See the full explanation below for the reasoning.
Question
Identify the missing words in the following sentence. The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.
Options
- Athe 'starting up a project' process is completed
- Bthe project mandate has been approved by the project board
- Cthe project board has agreed the project strategies
- Dcorporate, programme management or the customer have authorized a project
How the community answered
(34 responses)- A82% (28)
- B6% (2)
- C9% (3)
- D3% (1)