Why can PRINCE2 be applied to any type of project?
The correct answer is B. Because it allows each member of the project management team to fully understand their role. See the full explanation below for the reasoning.
Question
Why can PRINCE2 be applied to any type of project?
Options
- ABecause it provides the project manager with procedures for managing project risks and issues
- BBecause it allows each member of the project management team to fully understand their role
- CBecause it separates the management of the project from the specialist work needed to deliver
- DBecause it provides the project manager with a planning procedure to plan the project more
How the community answered
(19 responses)- A5% (1)
- B68% (13)
- C11% (2)
- D16% (3)