What action is taken as part of the 'controlling a stage' process? 1. Create an exception plan 2. Authorize work to be done 3. Take corrective action 4. Obtain approvals for completed products

Options

  • A1 and 2
  • B2 and 3
  • C3 and 4
  • D1 and 4