PRINCE2-FOUNDATION · Question #882

What action is taken as part of the 'controlling a stage' process? 1. Create an exception plan 2. Authorize work to be done 3. Take corrective action 4. Obtain approvals for completed products

The correct answer is B. 2 and 3. stage-process-in-prince2

Business Management

Question

What action is taken as part of the 'controlling a stage' process? 1. Create an exception plan 2. Authorize work to be done 3. Take corrective action 4. Obtain approvals for completed products

Options

  • A1 and 2
  • B2 and 3
  • C3 and 4
  • D1 and 4

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    79% (19)
  • C
    4% (1)
  • D
    13% (3)

Explanation

stage-process-in-prince2

Topics

#PRINCE2#controlling a stage#work authorization#corrective action