Which is a key decision made during the 'directing a project' process?
The correct answer is B. Approve the project manager role description. process-in-prince2
Business Management
Question
Which is a key decision made during the 'directing a project' process?
Options
- ASelect and appoint the project executive
- BApprove the project manager role description
- CConfirm that the benefits management approach addresses all expected benefits
- DApprove the proposed project mandate
How the community answered
(43 responses)- A5% (2)
- B77% (33)
- C14% (6)
- D5% (2)
Explanation
process-in-prince2
Topics
#PRINCE2#directing a project#project manager approval#project governance