Which is a key decision made during the 'directing a project' process?

The correct answer is B. Approve the project manager role description. process-in-prince2

Business Management

Question

Which is a key decision made during the 'directing a project' process?

Options

  • ASelect and appoint the project executive
  • BApprove the project manager role description
  • CConfirm that the benefits management approach addresses all expected benefits
  • DApprove the proposed project mandate

How the community answered

(43 responses)
  • A
    5% (2)
  • B
    77% (33)
  • C
    14% (6)
  • D
    5% (2)

Explanation

process-in-prince2

Topics

#PRINCE2#directing a project#project manager approval#project governance