Which should be provided by a project mandate?

The correct answer is A. Terms of reference. See the full explanation below for the reasoning.

Question

Which should be provided by a project mandate?

Options

  • ATerms of reference
  • BDetailed Business Case
  • CStage tolerances
  • DInitiation Stage Plan

How the community answered

(22 responses)
  • A
    73% (16)
  • B
    14% (3)
  • C
    5% (1)
  • D
    9% (2)