PeopleCert
PRINCE2-FOUNDATION · Question #874
Which should be provided by a project mandate?
The correct answer is A. Terms of reference. See the full explanation below for the reasoning.
Question
Which should be provided by a project mandate?
Options
- ATerms of reference
- BDetailed Business Case
- CStage tolerances
- DInitiation Stage Plan
How the community answered
(22 responses)- A73% (16)
- B14% (3)
- C5% (1)
- D9% (2)
Community Discussion
No community discussion yet for this question.