Which should be provided by corporate or programme management before the Starting up a Project process commences?
The correct answer is B. Sufficient information to identify the prospective Executive. See the full explanation below for the reasoning.
Question
Which should be provided by corporate or programme management before the Starting up a Project process commences?
Options
- AA Project Brief
- BSufficient information to identify the prospective Executive
- CThe Project Initiation Documentation
- DAuthority to initiate a project
How the community answered
(63 responses)- A11% (7)
- B83% (52)
- C5% (3)
- D2% (1)