PeopleCert
PRINCE2-FOUNDATION · Question #827
Which product identifies the management stages and timescales of a project?
The correct answer is C. Project Plan. See the full explanation below for the reasoning.
Question
Which product identifies the management stages and timescales of a project?
Options
- AProject Brief
- BProject Product Description
- CProject Plan
- DInitiation Stage Plan
How the community answered
(56 responses)- A7% (4)
- B13% (7)
- C77% (43)
- D4% (2)
Community Discussion