What is the first task of product-based planning?

The correct answer is B. Write the Project Product Description. See the full explanation below for the reasoning.

Question

What is the first task of product-based planning?

Options

  • AProduce the Initiation Stage Plan
  • BWrite the Project Product Description
  • CIdentify dependencies
  • DCreate the product breakdown structure

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    74% (28)
  • C
    11% (4)
  • D
    13% (5)