nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #802

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

The correct answer is B. Manage by exception. See the full explanation below for the reasoning.

Question

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

Options

  • AManage by stages
  • BManage by exception
  • CContinued business justification
  • DLearn from experience

How the community answered

(29 responses)
  • A
    17% (5)
  • B
    72% (21)
  • C
    3% (1)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice