Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
The correct answer is B. Manage by exception. See the full explanation below for the reasoning.
Question
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
Options
- AManage by stages
- BManage by exception
- CContinued business justification
- DLearn from experience
How the community answered
(29 responses)- A17% (5)
- B72% (21)
- C3% (1)
- D7% (2)