PRINCE2-FOUNDATION · Question #801

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

The correct answer is B. Cross-functional. See the full explanation below for the reasoning.

Question

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

Options

  • AChange
  • BCross-functional
  • CUnique
  • DRisk

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    86% (25)
  • C
    7% (2)
  • D
    3% (1)