InPRINCE2alpotentialchangesaredealtwithas...?

The correct answer is C. Project Issues. See the full explanation below for the reasoning.

Question

InPRINCE2alpotentialchangesaredealtwithas…?

Options

  • AConfiguration items
  • BRequests For Change
  • CProject Issues
  • DException Reports
  • EAction items

How the community answered

(33 responses)
  • A
    9% (3)
  • C
    76% (25)
  • D
    12% (4)
  • E
    3% (1)

Community Discussion

No community discussion yet for this question.