PRINCE2-FOUNDATION · Question #8
InPRINCE2alpotentialchangesaredealtwithas...?
The correct answer is C. Project Issues. See the full explanation below for the reasoning.
Question
InPRINCE2alpotentialchangesaredealtwithas…?
Options
- AConfiguration items
- BRequests For Change
- CProject Issues
- DException Reports
- EAction items
How the community answered
(33 responses)- A9% (3)
- C76% (25)
- D12% (4)
- E3% (1)