PRINCE2-FOUNDATION · Question #7
Which document reviews actual achievements against the Project Initiation Document?
The correct answer is A. End Project Report. See the full explanation below for the reasoning.
Question
Which document reviews actual achievements against the Project Initiation Document?
Options
- AEnd Project Report
- BPost-Project Review
- CLessons Learned Report
- DFollow-On Action Recommendations
How the community answered
(52 responses)- A77% (40)
- B4% (2)
- C13% (7)
- D6% (3)