Which is NOT included in the PRINCE2 definition of a project?
The correct answer is C. A project is part of 'business as usual'. See the full explanation below for the reasoning.
Question
Which is NOT included in the PRINCE2 definition of a project?
Options
- AA project is a temporary organization
- BA project's purpose is to deliver one or more business products
- CA project is part of 'business as usual'
- DA project is based on an agreed Business Case
How the community answered
(22 responses)- A5% (1)
- B5% (1)
- C77% (17)
- D14% (3)