PRINCE2-FOUNDATION · Question #791

Which is NOT included in the PRINCE2 definition of a project?

The correct answer is C. A project is part of 'business as usual'. See the full explanation below for the reasoning.

Question

Which is NOT included in the PRINCE2 definition of a project?

Options

  • AA project is a temporary organization
  • BA project's purpose is to deliver one or more business products
  • CA project is part of 'business as usual'
  • DA project is based on an agreed Business Case

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    77% (17)
  • D
    14% (3)