Question
Which is NOT included in the PRINCE2 definition of a project?
Options
- AA project is a temporary organization
- BA project's purpose is to deliver one or more business products
- CA project is part of 'business as usual'
- DA project is based on an agreed Business Case
Unlock PRINCE2-FOUNDATION to see the answer