PRINCE2-FOUNDATION · Question #790

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

The correct answer is B. Quality. See the full explanation below for the reasoning.

Question

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

Options

  • ABenefits
  • BQuality
  • CRisk
  • DScope

How the community answered

(51 responses)
  • A
    12% (6)
  • B
    80% (41)
  • C
    4% (2)
  • D
    4% (2)