PeopleCert
PRINCE2-FOUNDATION · Question #790
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
The correct answer is B. Quality. See the full explanation below for the reasoning.
Question
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
Options
- ABenefits
- BQuality
- CRisk
- DScope
How the community answered
(51 responses)- A12% (6)
- B80% (41)
- C4% (2)
- D4% (2)