Which does the Executive need to ensure is in place before the project is initiated?
The correct answer is B. An understanding of how the project will contribute to corporate objectives. See the full explanation below for the reasoning.
Question
Which does the Executive need to ensure is in place before the project is initiated?
Options
- AAll Work Packages are authorized
- BAn understanding of how the project will contribute to corporate objectives
- CThe Project Plan has been approved
- DThe Project Initiation Documentation is complete
How the community answered
(55 responses)- A5% (3)
- B78% (43)
- C13% (7)
- D4% (2)