Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
The correct answer is B. Those who will manage the project on a day-to-day basis. See the full explanation below for the reasoning.
Question
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
Options
- AThose with a financial interest in the project
- BThose who will manage the project on a day-to-day basis
- CThose who will specify the desired outputs of the project
- DThose who will create the project's outputs
How the community answered
(31 responses)- A6% (2)
- B84% (26)
- C6% (2)
- D3% (1)