PRINCE2-FOUNDATION · Question #559

Which role is the key decision-maker on the project management team?

The correct answer is D. Executive. See the full explanation below for the reasoning.

Question

Which role is the key decision-maker on the project management team?

Options

  • ACorporate or programme management
  • BChange Authority
  • CProject Manager
  • DExecutive

How the community answered

(32 responses)
  • A
    16% (5)
  • B
    3% (1)
  • C
    9% (3)
  • D
    72% (23)