PeopleCert
PRINCE2-FOUNDATION · Question #559
Which role is the key decision-maker on the project management team?
The correct answer is D. Executive. See the full explanation below for the reasoning.
Question
Which role is the key decision-maker on the project management team?
Options
- ACorporate or programme management
- BChange Authority
- CProject Manager
- DExecutive
How the community answered
(32 responses)- A16% (5)
- B3% (1)
- C9% (3)
- D72% (23)
Community Discussion