PRINCE2-FOUNDATION · Question #558

During project initiation, who determines the use of a Change Authority and whether a change budget will be used?

The correct answer is B. Change Authority. See the full explanation below for the reasoning.

Question

During project initiation, who determines the use of a Change Authority and whether a change budget will be used?

Options

  • AProject Board
  • BChange Authority
  • CProject Manager
  • DCorporate or Programme Management

How the community answered

(58 responses)
  • A
    14% (8)
  • B
    74% (43)
  • C
    7% (4)
  • D
    5% (3)