Who is responsible for the project producing a result that is capable of achieving the benefits defined in the Business Case?
The correct answer is B. The Project Manager. See the full explanation below for the reasoning.
Question
Who is responsible for the project producing a result that is capable of achieving the benefits defined in the Business Case?
Options
- AThe Executive
- BThe Project Manager
- CThe Senior User
- DThe entire Project Board
How the community answered
(40 responses)- A13% (5)
- B78% (31)
- C3% (1)
- D8% (3)