Which individual role is ultimately accountable for the project?
The correct answer is C. Executive. See the full explanation below for the reasoning.
Question
Which individual role is ultimately accountable for the project?
Options
- AProject Manager
- BSenior Supplier
- CExecutive
- DSenior User
How the community answered
(18 responses)- A11% (2)
- B11% (2)
- C72% (13)
- D6% (1)