nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #485

The Business Case describes the reasons for undertaking the project based on estimated costs, the major risks and what else?

The correct answer is D. Expected business benefits. See the full explanation below for the reasoning.

Question

The Business Case describes the reasons for undertaking the project based on estimated costs, the major risks and what else?

Options

  • AApproach to deliver the chosen business solution
  • BMeasurable acceptance criteria
  • CProject's products to be produced
  • DExpected business benefits

How the community answered

(47 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    15% (7)
  • D
    77% (36)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice