PRINCE2-FOUNDATION · Question #484

The information regarding why the project is required is documented in which product?

The correct answer is A. Business Case. See the full explanation below for the reasoning.

Question

The information regarding why the project is required is documented in which product?

Options

  • ABusiness Case
  • BBenefits Review Plan
  • CProject Product Description
  • DProject approach

How the community answered

(34 responses)
  • A
    82% (28)
  • B
    6% (2)
  • C
    3% (1)
  • D
    9% (3)