Which of the following is FALSE regarding PRINCE2 principles?
The correct answer is A. A project should have a customer/supplier environment. See the full explanation below for the reasoning.
Question
Which of the following is FALSE regarding PRINCE2 principles?
Options
- AA project should have a customer/supplier environment
- BA project should manage by exception
- CA project should focus on products
- DA project should be tailored to suit the project environment
How the community answered
(39 responses)- A85% (33)
- B8% (3)
- C3% (1)
- D5% (2)