Which of the following is FALSE regarding PRINCE2 principles?

The correct answer is A. A project should have a customer/supplier environment. See the full explanation below for the reasoning.

Question

Which of the following is FALSE regarding PRINCE2 principles?

Options

  • AA project should have a customer/supplier environment
  • BA project should manage by exception
  • CA project should focus on products
  • DA project should be tailored to suit the project environment

How the community answered