PRINCE2-FOUNDATION · Question #466
What characteristic relates to a project having a defined start and defined end?
The correct answer is C. Temporary in nature. See the full explanation below for the reasoning.
Question
What characteristic relates to a project having a defined start and defined end?
Options
- AUniqueness
- BUncertainty
- CTemporary in nature
- DIntroduces change
How the community answered
(17 responses)- A12% (2)
- B6% (1)
- C76% (13)
- D6% (1)