nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #39

Which process provides the information needed for the Project Board to assess the continuing viability of the project?

The correct answer is D. Managing Stage Boundaries. See the full explanation below for the reasoning.

Question

Which process provides the information needed for the Project Board to assess the continuing viability of the project?

Options

  • AStarting up a Project
  • BClosing a Project
  • CPlanning
  • DManaging Stage Boundaries

How the community answered

(21 responses)
  • A
    14% (3)
  • B
    10% (2)
  • C
    5% (1)
  • D
    71% (15)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice