PRINCE2-FOUNDATION · Question #38

Which step is NOT part of" Acepting a Work Package"?

The correct answer is C. Monitor and control the risks associated with the Work Package. See the full explanation below for the reasoning.

Question

Which step is NOT part of“ Acepting a Work Package”?

Options

  • AUnderstand the reporting requirements
  • BAgree tolerance margins for the Work Package
  • CMonitor and control the risks associated with the Work Package
  • DProduce a Team Plan which shows that the Work Package can be completed within the

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    13% (4)
  • C
    78% (25)
  • D
    6% (2)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice