PRINCE2-FOUNDATION · Question #35

The Project Board has three responsibilities towards the management of risk. Which of the following options is the FALSE one?

The correct answer is C. Identifying, recording and regularly reviewing risks. See the full explanation below for the reasoning.

Question

The Project Board has three responsibilities towards the management of risk. Which of the following options is the FALSE one?

Options

  • ANotifying the Project Manager of any external risk exposure to the project
  • BMaking decisions on recommended reactions to risk
  • CIdentifying, recording and regularly reviewing risks
  • DStriking a balance between levels of risk and potential benefits

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    71% (20)
  • D
    18% (5)