Which of these is mandatory in a PRINCE2 project?

The correct answer is C. The use of Stages. See the full explanation below for the reasoning.

Question

Which of these is mandatory in a PRINCE2 project?

Options

  • AThe use of Team Managers
  • BThe use of Exception Plans
  • CThe use of Stages
  • DThe use of Product Checklists

How the community answered

(45 responses)
  • A
    13% (6)
  • B
    7% (3)
  • C
    78% (35)
  • D
    2% (1)