Are the following statements true or false? 1 Delegated Project Assurance roles report directly to corporate or programme management 2 In PRINCE2 the Project Manager role must be full time 3 A…

The correct answer is B. Only the third is true. See the full explanation below for the reasoning.

Question

Are the following statements true or false? 1 Delegated Project Assurance roles report directly to corporate or programme management 2 In PRINCE2 the Project Manager role must be full time 3 A project management structure is a temporary structure

Options

  • AAll three are false
  • BOnly the third is true
  • COnly the first is false
  • DThe second and third are true

How the community answered

(51 responses)
  • A
    16% (8)
  • B
    75% (38)
  • C
    4% (2)
  • D
    6% (3)