PRINCE2-FOUNDATION · Question #28
Are the following statements true or false? 1 Delegated Project Assurance roles report directly to corporate or programme management 2 In PRINCE2 the Project Manager role must be full time 3 A…
The correct answer is B. Only the third is true. See the full explanation below for the reasoning.
Question
Are the following statements true or false? 1 Delegated Project Assurance roles report directly to corporate or programme management 2 In PRINCE2 the Project Manager role must be full time 3 A project management structure is a temporary structure
Options
- AAll three are false
- BOnly the third is true
- COnly the first is false
- DThe second and third are true
How the community answered
(51 responses)- A16% (8)
- B75% (38)
- C4% (2)
- D6% (3)