PRINCE2-FOUNDATION · Question #27
In which sub-process are Checkpoint Reports created?
The correct answer is A. Executing a Work Package. See the full explanation below for the reasoning.
Question
In which sub-process are Checkpoint Reports created?
Options
- AExecuting a Work Package
- BAssessing Progress
- CReporting Highlights
- DReviewing Stage Status
How the community answered
(51 responses)- A84% (43)
- B4% (2)
- C10% (5)
- D2% (1)