Which of the following is NOT a PRINCE2 Principle?

The correct answer is B. Project manage by process. See the full explanation below for the reasoning.

Question

Which of the following is NOT a PRINCE2 Principle?

Options

  • AContinued business justification
  • BProject manage by process
  • CManage by stages
  • DTailor to suit the project environment

How the community answered

(19 responses)
  • B
    84% (16)
  • C
    5% (1)
  • D
    11% (2)