PRINCE2-FOUNDATION · Question #256
In respect of the project's organization structure, one of the seven principles of PRINCE2 is that every project must have which one of the following?
The correct answer is A. Defined and agreed roles and responsibilities with an organization structure that engages. See the full explanation below for the reasoning.
Question
In respect of the project's organization structure, one of the seven principles of PRINCE2 is that every project must have which one of the following?
Options
- ADefined and agreed roles and responsibilities with an organization structure that engages
- BPeople allocated to clearly defined management jobs, assigned to them on a one-to-one
- CAs many stakeholders as possible from the customer environment involved in key
- DStakeholders who are responsible, accountable, consulted and informed throughout every
How the community answered
(16 responses)- A81% (13)
- C6% (1)
- D13% (2)
Community Discussion