PRINCE2-FOUNDATION · Question #178

Which report does the Project Manager receive on a regular basis?

The correct answer is B. Checkpoint Report. See the full explanation below for the reasoning.

Question

Which report does the Project Manager receive on a regular basis?

Options

  • AHighlight Report
  • BCheckpoint Report
  • CIssue Report
  • DException Report

How the community answered

(59 responses)
  • A
    2% (1)
  • B
    85% (50)
  • C
    5% (3)
  • D
    8% (5)