PRINCE2-FOUNDATION · Question #178
Which report does the Project Manager receive on a regular basis?
The correct answer is B. Checkpoint Report. See the full explanation below for the reasoning.
Question
Which report does the Project Manager receive on a regular basis?
Options
- AHighlight Report
- BCheckpoint Report
- CIssue Report
- DException Report