Who does PRINCE2TM say may re-evaluate the priority of an issue after impact analysis?

The correct answer is D. The Project Board. See the full explanation below for the reasoning.

Question

Who does PRINCE2TM say may re-evaluate the priority of an issue after impact analysis?

Options

  • AThe Team Manager
  • BThose with assurance responsibilities
  • CThe Author
  • DThe Project Board