Who is responsible for confirming stage and project progress against agreed tolerances?

The correct answer is C. Project Assurance. See the full explanation below for the reasoning.

Question

Who is responsible for confirming stage and project progress against agreed tolerances?

Options

  • AProject Support
  • BExecutive
  • CProject Assurance
  • DProject Manager

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    85% (34)
  • D
    8% (3)