There are two time driven controls in PRINCE2 which are they'?

The correct answer is A. Highlight and End Stage Reports. See the full explanation below for the reasoning.

Question

There are two time driven controls in PRINCE2 which are they’?

Options

  • AHighlight and End Stage Reports
  • BHighlight and Checkpoint Reports
  • CCheckpoint and End Project Reports
  • DHighlight and Lessons Reports

How the community answered

(29 responses)
  • A
    72% (21)
  • B
    14% (4)
  • C
    3% (1)
  • D
    10% (3)