PRINCE2-FOUNDATION · Question #116

Who is responsible for ensuring That Communication Management Strategy is appropriate and that planned communication activities actually take place?

The correct answer is A. Project Assurance. See the full explanation below for the reasoning.

Question

Who is responsible for ensuring That Communication Management Strategy is appropriate and that planned communication activities actually take place?

Options

  • AProject Assurance
  • BProject Manager
  • CCorporate or Programme Management
  • DProject Support

How the community answered

(30 responses)
  • A
    73% (22)
  • B
    3% (1)
  • C
    10% (3)
  • D
    13% (4)